Liverpool Cbd Trunk Drainage Works

Major sewer relocation works, Installation of new 1800mm dia, 1350mm dia and 1050 mm dia drainage pipes in Liverpool CBD. Installation of new Rocla 750 GPT. Construction of new drainage structures, demolition & reconstruction of K & G, driveways/Footpath. Construction of new road pavement, Signage & line marking works.

COMPLETION DATE: SEPTEMBER 2010
CLIENT: LIVERPOOL CITY COUNCIL
SUPERINTENDENT: RAVI WIJERATNE – 02 9821 9348

Interallotment Drainage

Installation of 375mm dia & 450mm dia drainage pipe culverts in Richmond rail corridor & construction of drainage structures.

COMPLETION DATE: 2009
CLIENT: HAWKESBURY CITY COUNCIL
SUPERINTENDENT: MATTHEW TORIOLA – 02 4560 4518

Chatswood Cbd Trunk Drainage Works Stages

Installation of new 1050mm dia, 750mm dia, 600mm and 450 dia drainage pipes in Chatswood CBD. Construction of 4 major inlet/outlet structures. Installation of GPT. Demolition & reconstruction of K & G. Construction of new road pavement. Line marking works. Traffic control.

COMPLETION DATE: DECEMBER 2010
CLIENT: WILLOUGHBY COUNCIL
SUPERINTENDENT: GEOFF DOUGLAS – 0417 270 546

Carlton Parade Roadworks – Punchbowl

Reconstruction of 700m of Kerb & Gutter, Kerb ramps, 25 Vehicular crossing reconstructed ,Construction of 100m of dish drains, storm water pit construction and relocation and adjustment to roof water outlets.

COMPLETION DATE: 2007
CLIENT: CANTERBURY COUNCIL
SUPERINTENDENT: RAY WILMSLEY

Bankstown Strategic Bus Corridor Works

Widen various road intersections to accommodate turning area for large buses. Work involves Telstra, watermain, power line and traffic signal relocation at three intersections in Bankstown and a new signalised pedestrian crossing at Chesterhill. Other works include drainage line upgrades, kerb and gutter work, road reconstruction and asphalt resheeting. Traffic control.

COMPLETION DATE: 2008
CLIENT: BANKSTOWN CITY COUNCIL
SUPERINTENDENT: ALLAN EL HASSAN – 0412 439722