The works involved the construction of the Epping Road Cycleway (Shared User Path) along the westbound side of Epping Road from Vimiera Rd to Herring Rd, Marsfield.

  • Works include demolition of any existing pathway, and/or removal of designated vegetation
  • Construct 4,050m2 of a nominally 3m wide shared user path
  • Construction and upgrade of kerb ramps and vehicular crossings
  • Traffic islands
  • Concrete/block retaining wall and associated pedestrian fencing
  • Low-Level Boardwalk
  • Restoration of turf adjacent to footpath
  • Line marking and signage installations
  • Revegetation and landscaping
COMPLETION DATE: Oct 2019
CLIENT: City of Ryde Council